🔥 Today Only: Save 30% on Premium — Offer Ends Soon! - Upgrade Now!

The Falkirk Wheel - IELTS Reading Answers & Explanations

From Cambridge IELTS 11 Academic Reading Test 1 · Part 2 · Questions 14–26

Reading Passage

The Falkirk Wheel

A unique engineering achievement

The Falkirk Wheel in Scotland is the world’s first and only rotating boat lift. Opened in 2002, it is central to the ambitious £84.5m Millennium Link project to restore navigability across Scotland by reconnecting the historic waterways of the Forth & Clyde and Union Canals.

The major challenge of the project lays in the fact that the Forth & Clyde Canal is situated 35 metres below the level of the Union Canal. Historically, the two canals had been joined near the town of Falkirk by a sequence of 11 locks – enclosed sections of canal in which the water level could be raised or lowered – that stepped down across a distance of 1.5 km. This had been dismantled in 1933, thereby breaking the link. When the project was launched in 1994, the British Waterways authority were keen to create a dramatic twenty-first-century landmark which would not only be a fitting commemoration of the Millennium, but also a lasting symbol of the economic regeneration of the region.

Numerous ideas were submitted for the project, including concepts ranging from rolling eggs to tilting tanks, from giant seesaws to overhead monorails. The eventual winner was a plan for the huge rotating steel boat lift which was to become The Falkirk Wheel. The unique shape of the structure is claimed to have been inspired by various sources, both manmade and natural, most notably a Celtic double headed axe, but also the vast turning propeller of a ship, the ribcage of a whale or the spine of a fish.

The various parts of The Falkirk Wheel were all constructed and assembled, like one giant toy building set, at Butterley Engineering’s Steelworks in Derbyshire, some 400 km from Falkirk. A team there carefully assembled the 1,200 tonnes of steel, painstakingly fitting the pieces together to an accuracy of just 10 mm to ensure a perfect final fit. In the summer of 2001, the structure was then dismantled and transported on 35 lorries to Falkirk, before all being bolted back together again on the ground, and finally lifted into position in five large sections by crane. The Wheel would need to withstand immense and constantly changing stresses as it rotated, so to make the structure more robust, the steel sections were bolted rather than welded together. Over 45,000 bolt holes were matched with their bolts, and each bolt was hand-tightened.

The Wheel consists of two sets of opposing axe-shaped arms, attached about 25 metres apart to a fixed central spine. Two diametrically opposed water-filled ‘gondolas’, each with a capacity of 360,000 litres, are fitted between the ends of the arms. These gondolas always weigh the same, whether or not they are carrying boats. This is because, according to Archimedes’ principle of displacement, floating objects displace their own weight in water. So when a boat enters a gondola, the amount of water leaving the gondola weighs exactly the same as the boat. This keeps the Wheel balanced and so, despite its enormous mass, it rotates through 180° in five and a half minutes while using very little power. It takes just 1.5 kilowatt-hours (5.4 MJ) of energy to rotate the Wheel -roughly the same as boiling eight small domestic kettles of water.

Boats needing to be lifted up enter the canal basin at the level of the Forth & Clyde Canal and then enter the lower gondola of the Wheel. Two hydraulic steel gates are raised, so as to seal the gondola off from the water in the canal basin. The water between the gates is then pumped out. A hydraulic clamp, which prevents the arms of the Wheel moving while the gondola is docked, is removed, allowing the Wheel to turn. In the central machine room an array of ten hydraulic motors then begins to rotate the central axle. The axle connects to the outer arms of the Wheel, which begin to rotate at a speed of 1/8 of a revolution per minute. As the wheel rotates, the gondolas are kept in the upright position by a simple gearing system. Two eight-metre-wide cogs orbit a fixed inner cog of the same width, connected by two smaller cogs travelling in the opposite direction to the outer cogs – so ensuring that the gondolas always remain level. When the gondola reaches the top, the boat passes straight onto the aqueduct situated 24 metres above the canal basin.

The remaining 11 metres of lift needed to reach the Union Canal is achieved by means of a pair of locks. The Wheel could not be constructed to elevate boats over the full 35-metre difference between the two canals, owing to the presence of the historically important Antonine Wall, which was built by the Romans in the second century AD. Boats travel under this wall via a tunnel, then through the locks, and finally on to the Union Canal.

Questions

Questions 14–19 True / False / Not Given

Do the following statements agree with the information given in the Reading Passage?

In boxes on your answer sheet, write

TRUE                if the statement agrees with the information

FALSE               if the statement contradicts the information

NOT GIVEN     if there is no information on this

14 The Falkirk Wheel has linked the Forth & Clyde Canal with the Union Canal for the first time in their history.
15 There was some opposition to the design of the Falkirk Wheel at first.
16 The Falkirk Wheel was initially put together at the location where its components were manufactured.
17 The Falkirk Wheel is the only boat lift in the world which has steel sections bolted together by hand.
18 The weight of the gondolas varies according to the size of boat being carried.
19 The construction of the Falkirk Wheel site took into account the presence of a nearby ancient monument.

Questions 20–26 Diagram Labeling

Label the diagram below.

Choose ONE WORD from the passage for each answer.

Write your answers in boxes on your answer sheet.

How a boat is lifted on the Falkirk Wheel

Cambridge IELTS 11 Academic Reading Test 1 - 20 - 26

20
21
22
23
24
25
26

Answers & Explanations Summary

# Answer Evidence Explanation
Q14 FALSE Historically, the two canals had been joined near the town of Falkirk by a sequence of 11 locks – enclosed sections of canal in which the water level could be raised or lowered – that stepped down across a distance of 1.5 km. Excerpt/Passage Explanation:
The passage talks about how the Forth & Clyde Canal and the Union Canal were historically connected near Falkirk by a series of locks.
Answer Explanation:
The answer states that the Falkirk Wheel did not link the two canals for the first time in their history.
Reason For Correctness:
The correct answer is FALSE because the excerpt clearly mentions that historically, the two canals were already joined near Falkirk by a sequence of locks, not for the first time through the Falkirk Wheel.
Q15 NOT GIVEN Numerous ideas were submitted for the project, including concepts ranging from rolling eggs to tilting tanks, from giant seesaws to overhead monorails. The eventual winner was a plan for the huge rotating steel boat lift which was to become The Falkirk Wheel. Excerpt/Passage Explanation:
The passage talks about different ideas that were suggested for a project, including a rotating steel boat lift known as The Falkirk Wheel.
Answer Explanation:
The answer means that the passage does not provide information about whether there was opposition to the design of the Falkirk Wheel at first.
Reason For Correctness:
The correct answer is 'NOT GIVEN' because the passage only mentions the ideas suggested for the project and the eventual selection of the rotating steel boat lift as the winner. There is no specific mention of any opposition to the design of the Falkirk Wheel.
Q16 TRUE The various parts of The Falkirk Wheel were all constructed and assembled, like one giant toy building set, at Butterley Engineering’s Steelworks in Derbyshire, some 400 km from Falkirk. Excerpt/Passage Explanation:
The passage talks about how The Falkirk Wheel's parts were built and put together at Butterley Engineering’s Steelworks in Derbyshire, which is far from Falkirk.
Answer Explanation:
The answer means that the statement agrees with the information given in the passage.
Reason For Correctness:
The correct answer is TRUE because the excerpt clearly states that the components of The Falkirk Wheel were constructed and assembled at a location in Derbyshire, not at Falkirk where the wheel is actually located. Therefore, the statement that the wheel was initially put together where its components were manufactured is true based on the provided information.
Q17 NOT GIVEN The Wheel would need to withstand immense and constantly changing stresses as it rotated, so to make the structure more robust, the steel sections were bolted rather than welded together. Excerpt/Passage Explanation:
The passage explains that to make The Falkirk Wheel stronger, the steel sections were bolted together instead of being welded.
Answer Explanation:
The answer means that the information whether the Falkirk Wheel is the only boat lift in the world with steel sections bolted together by hand is not provided in the passage.
Reason For Correctness:
The correct answer is 'NOT GIVEN' because the passage does not state or compare whether the Falkirk Wheel is the only boat lift in the world with steel sections bolted together by hand. Therefore, the information to confirm if the statement is true or false is not given in the passage.
Q18 FALSE These gondolas always weigh the same, whether or not they are carrying boats. Excerpt/Passage Explanation:
The passage says that the gondolas always have the same weight, regardless of whether they are carrying boats or not.
Answer Explanation:
The answer states that the weight of the gondolas does not change based on the size of the boat being carried.
Reason For Correctness:
The correct answer is FALSE because the given answer aligns with the information in the passage, which clearly mentions that the gondolas maintain a consistent weight regardless of carrying boats. Therefore, the statement about the weight varying based on boat size is incorrect.
Q19 TRUE The Wheel could not be constructed to elevate boats over the full 35-metre difference between the two canals, owing to the presence of the historically important Antonine Wall, which was built by the Romans in the second century AD. Excerpt/Passage Explanation:
The passage tells us that the Falkirk Wheel couldn't be built to elevate boats fully because of an ancient wall nearby.
Answer Explanation:
The answer states that the construction of the Falkirk Wheel site considered the nearby ancient monument.
Reason For Correctness:
The correct answer is TRUE because the passage clearly mentions that the presence of the historic Antonine Wall influenced the construction of the Wheel. Therefore, the statement aligns with the information provided.
Q20 gates Two hydraulic steel gates are raised, so as to seal the gondola off from the water in the canal basin. Excerpt/Passage Explanation:
The passage talks about two gates made of hydraulic steel being lifted in order to block off or close the area where the boat is located from the water in the canal basin.
Answer Explanation:
The answer refers to the 'gates' which are essentially large doors that can be raised or lowered to control the flow of water and separate different sections.
Reason For Correctness:
The correct answer is 'gates' because the excerpt specifically mentions 'hydraulic steel gates' being raised to separate the boat from the water in the canal basin, indicating that the gates play a key role in the process of lifting the boat on the Falkirk Wheel.
Q21 clamp A hydraulic clamp, which prevents the arms of the Wheel moving while the gondola is docked, is removed, allowing the Wheel to turn. Excerpt/Passage Explanation:
The passage talks about a tool called a 'clamp.' This tool is used to prevent the arms of the Falkirk Wheel from moving when a boat is docked.
Answer Explanation:
The answer is a tool named 'clamp' that is mentioned in the excerpt.
Reason For Correctness:
The correct answer is 'clamp' because the excerpt specifically mentions a hydraulic clamp being used in the process of lifting a boat on the Falkirk Wheel. The clamp's function is to prevent the movement of the wheel's arms when a boat is docked, allowing the wheel to turn efficiently.
Q22 axle In the central machine room an array of ten hydraulic motors then begins to rotate the central axle. Excerpt/Passage Explanation:
The passage is describing how the Falkirk Wheel, a boat lift, works. It says that in a special room, there are ten strong machines that make something turn around.
Answer Explanation:
The answer is 'axle'. An axle is a rod or a bar that turns around to make something move.
Reason For Correctness:
The correct answer is 'axle' because the passage says 'rotate the central axle', which means the ten hydraulic motors make the central axle turn around. This is why 'axle' is the correct answer.
Q23 cogs Two eight-metre-wide cogs orbit a fixed inner cog of the same width, connected by two smaller cogs travelling in the opposite direction to the outer cogs – so ensuring that the gondolas always remain level. Excerpt/Passage Explanation:
The passage describes a mechanism where two larger cogs rotate around a fixed central cog, connected by two smaller cogs moving in the opposite direction. This setup ensures that the gondolas, or compartments on the wheel, always stay balanced and horizontal.
Answer Explanation:
The answer refers to the gear-like components (cogs) mentioned in the passage that play a crucial role in the lifting mechanism of the boat on the Falkirk Wheel.
Reason For Correctness:
The correct answer 'cogs' is directly taken from the passage, which clearly states the presence and function of these mechanical parts in explaining how a boat is lifted on the Falkirk Wheel.
Q24 aqueduct When the gondola reaches the top, the boat passes straight onto the aqueduct situated 24 metres above the canal basin. Excerpt/Passage Explanation:
The passage talks about a boat being lifted by a special structure called a gondola. When the gondola gets to the top, the boat goes onto a channel for water called an aqueduct. This aqueduct is 24 metres above the ground.
Answer Explanation:
The answer, 'aqueduct', is a word that means a channel for water.
Reason For Correctness:
The correct answer 'aqueduct' is found in the excerpt. The excerpt states that the boat passes straight onto the 'aqueduct' after the gondola reaches the top. This means the aqueduct is a channel or path that allows the boat to continue moving after being lifted by the gondola.
Q25 wall Boats travel under this wall via a tunnel, then through the locks, and finally on to the Union Canal. Excerpt/Passage Explanation:
The passage mentions that boats pass under a wall through a tunnel, then go through locks, and reach the Union Canal.
Answer Explanation:
The answer 'wall' refers to a solid structure that the boats travel under before continuing on their route.
Reason For Correctness:
The correct answer is 'wall' because the passage specifically describes the boats traveling under this structure, indicating its role in the process of how a boat is lifted on the Falkirk Wheel.
Q26 locks The remaining 11 metres of lift needed to reach the Union Canal is achieved by means of a pair of locks. Excerpt/Passage Explanation:
The passage explains that the boat is lifted by using a pair of locks to achieve the remaining lift needed to reach the Union Canal.
Answer Explanation:
The answer 'locks' refers to a mechanism that allows boats to move between different water levels in a canal by controlling the water flow.
Reason For Correctness:
The correct answer is 'locks' because the excerpt specifically mentions that the lift needed for the boat is achieved by using a pair of locks. Locks are an essential part of canal systems and are used to raise or lower boats between stretches of different water levels.

Leave a Reply

Your email address will not be published. Required fields are marked *

We have detected unusual activity on your device.
Please verify your identity to continue.
Note: This verification step won't sign you in. If you have a premium account, please log in to access the service as usual.
Google/Gmail Verification
Or verify using Email/Code
We've sent a verification code to:
youremail@gmail.com (Not your email?)
Enter it below to complete the verification process.
Ensure your email address is correct, your inbox is not full, and you check your spam folder. If no email arrives, consider using an alternative email.
You will need a Premium plan to perform your action!
Note: If you already have a premium account, please log in to access our services as usual.

Plans & Pricing

Our mission is to make quality education accessible for everyone.
However, to keep our hardworking team running and this service alive, we genuinely need your support!
By opting for a premium plan, not only do you sustain us in achieving the mission, but you also unlock advanced features to enrich your learning experience.

Free

For learners who aren't pressed for time

What's included on Free
100+ Cambridge IELTS Tests
Instant IELTS Writing Task 1 & 2 Evaluation (2 times/month)
Instant IELTS Speaking Part 1, 2, & 3 Evaluation (5 times/month)
Instant IELTS Writing Task 1 & 2 Essay Generator (2 times/month)
500+ Dictation & Shadowing Exercises
100+ Pronunciation Exercises
Flashcards
Other Advanced Tools

Premium

For those serious about advancing their English proficiency, and for IELTS candidates aspiring to boost their band score by 1-2 points (especially in writing & speaking) in just 30 days or less

What's included on Premium
Save Your IELTS Test Progress
Unlock All Courses & IELTS Tests
Unlimited AI Conversations
Unlimited AI Writing Enhancement Exercises
Unlimited IELTS Writing Task 1 & 2 Evaluation
Unlimited IELTS Speaking Part 1, 2, & 3 Evaluation
Checked Answers Will Not Be Published
Unlimited IELTS Writing Task 1 & 2 Essay Generator
Unlimited IELTS Speaking Part 1, 2, & 3 Sample Generator
Unlimited Usage Of Advanced Tools
Priority Support within 24h (12-month plan only)

Due to the nature of our service and the provided free trials, payments are non-refundable.
Nếu bạn là người Việt Nam và không có hoặc không muốn trả bằng credit/debit cards, bạn có thể thanh toán bằng phương thức chuyển khoản:



Chọn gói:
419,000₫ 277,000 ₫ cho gói 1 tháng (chỉ 9,233₫/ngày)
1,239,000₫ 597,000 ₫ cho gói 3 tháng (chỉ 6,633₫/ngày)
2,469,000₫ 1,027,000 ₫ cho gói 6 tháng (chỉ 5,706₫/ngày)
4,929,000₫ 1,417,000 ₫ cho gói 12 tháng (chỉ 3,936₫/ngày)


Sau khi chuyển khoản, vui lòng đợi trình duyệt tự động điều hướng bạn trở lại Engnovate và bạn sẽ ngay lập tức nhận được mã kích hoạt tài khoản premium.
Nếu có lỗi xảy ra, bạn có thể liên hệ với team thông qua một trong các phương thức: email đến helloengnovate@gmail.com hoặc nhắn tin qua facebook.com/engnovate.
Vì toàn bộ công cụ trên website đều có thể sử dụng thử miễn phí, Engnovate không hỗ trợ hoàn tiền.