The diagram provides a detailed overview of the stages involved in constructing a new project, along with the time allocated to each stage over a 16-week period.
Overall, the process is clearly divided into two main phases:preparation rand construction.The former occupies roughly the first half of the timeline and consists mainly of planning and administrative tasks, whereas the latter involves the phisycal building of the house and continues until completion.
During the preparation phase,the process begins with assessing the site in the first week,followed by drawing up plans, which takes approximately two weeks.Subsequently, approval is obtained before builders are hired.This is followed by purchasing insurance and preparing the site, both of which are completed by around week 8.
From week 9 onwards, the construction phase commences with the pouring of the concrete foundation. Once this is completed, the frame of the house is erected, after which the walls and roof are installed.In the subsequent stages, windows are fitted, followed by the installation of plumbing and electrical systems.Finally, the process concludes with painting both the interior and exterior,bringing the project to completion in week 16.